Description
BSE announces phased rollout of enhanced market data streams with parallel support for existing NFCAST format until October 2025.
Summary
BSE announces a phased approach for implementing enhanced market data streams, providing parallel support for existing NFCAST format alongside new format for a limited period. The rollout extends from September 8 to October 13, 2025, with different go-live dates for each segment.
Key Points
- Parallel run of existing and new NFCAST format for limited period based on member feedback
- EOBI/EMDI/MDI streams will switch directly to new format without parallel support
- New multicast IP and port assignments for enhanced data streams
- Mock trading sessions scheduled before each segment go-live
- Different implementation timeline for each trading segment
Regulatory Changes
- Implementation of enhanced market data stream formats across all trading segments
- New multicast IP and port configurations for improved data delivery
- Phased migration approach replacing direct switchover originally planned
Compliance Requirements
- Trading members must update systems to support new data stream formats
- Third-party trading application vendors must undertake necessary system development
- Migration from existing to new NFCAST format must be completed before discontinuation dates
- Testing participation in mock trading sessions recommended
Important Dates
- September 6, 2025: Mock trading for Currency Derivatives, Commodities Derivatives & EGR
- September 8, 2025: Go-live for Currency Derivatives, Commodities Derivatives & EGR (new format)
- September 13, 2025: Mock trading for Equity Derivatives
- September 15, 2025: Go-live for Equity Derivatives (new format)
- September 20, 2025: Mock trading for Equity segment
- September 22, 2025: Go-live for Equity segment (new format)
- October 3, 2025: Last day of parallel NFCAST for Currency/Commodities Derivatives & EGR
- October 6, 2025: Discontinuation of existing NFCAST format for Currency/Commodities Derivatives & EGR
- October 10, 2025: Last day of parallel NFCAST for Equity segment
- October 13, 2025: Discontinuation of existing NFCAST format for Equity segment
Impact Assessment
- High operational impact on all trading members and technology vendors requiring system updates
- Reduced disruption risk through parallel run approach compared to direct switchover
- Enhanced market data delivery capabilities once fully implemented
- Technology infrastructure upgrade affecting real-time trading operations
- Member preparation time extended through phased implementation and mock sessions
Impact Justification
Major technology upgrade affecting all trading members and vendors with specific implementation deadlines and system changes required